Installation Matters:

1. Energy-saving dryer stretch level gauge is usually installed on the top.

2. There should be no interference in the installation of the probe, such as the agitator and the inlet.

3. The probe cannot be bent and stressed, and is not allowed to be subjected to large impact or vibration. The magnetic float on the probe should be able to slide up and down freely and cannot be blocked by other objects.

4. The liquid level gauge must be installed vertically, and the installation slope should not be greater than 5 degrees.

5. When the liquid level gauge is used in flammable, explosive, corrosive steam and liquid, it must be protected by protective measures.

6. The connection cable of the level gauge must avoid high-power power, RF signal source and other noisy transmission lines.